Professional design
Have a qualified designer prepare the foundation around the machine, maximum workpiece load and local soil conditions.
SUFENG CNC南京速锋数控A practical site-preparation summary from the company archive. Final construction must follow the project foundation drawing and qualified local engineering advice.
Horizontal and gantry machining centers require planned load capacity, vibration control and adequate curing time.
Have a qualified designer prepare the foundation around the machine, maximum workpiece load and local soil conditions.
The archived guideline uses at least 10 t/m² and C25–C30 concrete as reference values; the project drawing remains authoritative.
Keep the machine away from vibration sources. Add isolation where needed and protect the pit from water, oil and corrosion.
Archived guidance limits full-length foundation flatness to 10 mm, followed by at least 28 days curing and 7 days preloading.
Reserve anchor pockets from the machine foundation drawing and use continuous, non-shrink high-strength grouting.
Confirm power, air, lifting access, transport route, chip handling and coolant facilities before delivery.
Delivery scope varies by machine and project. Installation, commissioning, training, acceptance and warranty terms follow the final quotation and contract.
This page is planning guidance only. It does not replace a project foundation drawing, local building code or professional engineering advice.